Systra 2020 Proposed BRT Routes
click on legend to highlight route
FEM 2025 Proposed BRT Routes
Key features include:
- Overall fleet requirement is around 5% larger.
- Better match with demand in corridor. Higher frequency of service and capacity in higher demand corridor sections.
- Better match with demand outside corridor. Lower proportion of route length in corridor (62% vs 46% average length in corridor).
- Significantly fewer transfers and higher demand can be expected.
- Larger coverage: 100km vs 70km of roads covered with BRT service (including BRT corridor).
- No transfer terminal needed, so Katsina Road station can be cancelled. Less need to consider transfer facilities at other locations along corridor. Additional off-corridor layover & turnaround facilities needed at route ends.
- Higher impacts on existing services in off-corridor segments.